PLANT UPGRADES TO TYNDRUM TREATMENT WORKS TRIPLES FILTER SCREENING CAPACITY

Tyndrum Wastewater Treatment Works in Stirlingshire, Scotland, has upgraded its process screening capacity to handle more than triple its original volume, increasing capacity from 3.2 litres per second to 10.6 L/s. WGM Engineering delivered the full design plus civils, construction, MEICA fit-out and commissioning for Scottish Water, completing the project in July after extensive testing.  The 1981-built plant’s age and location within a tourist-dependent village created significant challenges. The plant had to remain operational throughout construction, requiring temporary screenings and over-ground pumping. “Installation faced unforeseen hurdles due to the age…

Read More